Question 4
[15 Marks]
Readthe newspaper article below and answer the questions thereafter.
LUTOMBIUNHAPPYABOUT DELAYEDROADWORKS
Project behind by more than two months
The project involves the upgrading of a 16.3-kilometre stretch of road, and began in October
last year.
Tuyeimo Haidula
2 DAY AGO - 2024-04-09 12:21:00
Roads Authority (RA) CEO Conrad Lutombi is not impressed with slow progress on a road
upgrade in the Oshikoto Region. This after the RA and the Road Fund Administration (RFA)
last week made a trip to inspect ongoing construction on the Engoyi-Omuntele road.
The project involves the upgrading of a 16.3-kilometre stretch, and began in October last year.
The construction was due to be completed by September, but according to Lutombi, the
project is behind by two-and-a-half months.
So far, only N$5 million of the allocated N$43 million for the project has been spent. "An
amount of N$20 million should have been spent on the project thus far. This is unacceptable
as it is a setback for the community which requires service delivery," he said, adding that only
six kilometres of the 16-kilometre road has been worked on.
"I am not happy, and I made it very clear during the meeting with the contractor and the
consultant, as well as the one official who is on this project. We need to pull up our socks,"
he said.
The RAwill do another follow-up to check on the project's progress in May, Lutombi said, and
will in the meantime issue the contractor a 21-day notice to accelerate the development
without compromising on quality.
"And those officials, we hold them accountable to make sure that they are on the project. We
can't stay in the office. Our work is here. If people are sitting in the office and there is a delay
and we are coming from Windhoek to come and find this, we cannot tolerate that, and we
are serious about that. If people don't want to work, they must go and find a job somewhere
else," Lutombi fumed.
RoadsContractor Company (RCC)acting CEODasius Nelumbu guaranteed that the project will
be completed by September as promised. He added that they will redouble efforts to ensure
the project is completed on time, even if it means they need to bring in a second or a third
team to meet the deadline.
Source: https://www.namibiansun.com/infrastructure/lutombi-unhappy-about-delayed-roadworks2024-04-09-111383
6