Civil Engineering for Planning
CEP610S
Question 1
The Regional Council where you are employed as a planner is embarking on an electrification capital
project in a newly established settlement area via below ground cabling, and you are sent to the
community to discuss the advantages and disadvantages of this below ground electrification option.
What are the advantages and disadvantages you would highlight to the community?
[8]
Question 2
During a public meeting with inhabitants of a newly proclaimed town your are asked to explain the
difference between high and middle order public facilities as the community members are expecting
these types of public facilities to be built in their town.
What would your explanation be?
[9]
Question 3
A 3500
A 3000
't: A 2500
GJ
a.. A 2000
GJ
....a. R 1500
e0 n R 1000
0
R 500
, ............ , ..•.,....•. TI .... .,, •... - ·-·--···•·
SANITATION
OPTIONS
..
.. "-.I-······-·"·-·····
··•·---_-__--------- I
I
._. __ _______ ........ ...................... .. _.. .,.,___________--_·_-_·-·,-1I-·-·····-··_.·.-•.··-·•···
,.. ·- fI , .•......
.,.
.._.,.__,._.,.
I
I
I
I
········---..".'.·•--·•
•••••
---,
-
Full -flush
Intermediate-flush
Aqua-privy
...I
I-
Pour-flush
VIP latrine
I
............. - ..................1................................. .
I
I
'
I
•.....1....................................... .
I
I
I
Bucket collection
25
50
75
density per dwelling unit
The graph above illustrates the impact of residential densities on the cost per erf to provide
sanitation options to those erven.
(a) Explain why increased residential densities impact on the cost of Full Flush systems positively
but has no impact on the Aqua Privy and VIP options.
(3)
First Opportunity Examination Question Paper
Page 2 of 5
June 2023