c) Ask the project team to repair the defect
d) Begin the claims administration process
15) A team member submits a draft of the requirements management plan to the project
manager for a review. The project manager notices that one of the components included in
the plan does not belong there. Which of the following components did the project manager
most likely notice?
a) A process that describes how the project requirements will be prioritized
b) The metrics that will be used and the rationale for using them
c) A process that specifies how a project scope statement will be prepared
d) How requirement activities will be planned, tracked, and reported
16) You are about to start planning for a large and complex project. Due to the size of the project
along with the regulatory and environmental considerations, the development of a detailed
project management plan will be critical. As a starting point for initial project planning, what
is the first thing you should do?
a) Conduct a project kick-off meeting to inform and engage stakeholders and gain
commitment
b) Review the project charter to understand the high-level information about the project
c) Begin the process of identifying stakeholders so they can be engaged as necessary for
project planning
d) Share the project scope statement with the project team for a common understanding
of project deliverables
17) You are facing problems decomposing the testing work package into the final activities
required to complete the work package. Detailed testing plans and activities cannot be
determined until the system is at least 50% developed and more details become available.
The system development work package will take at least three months to complete. What is
the best way to resolve this problem?
a) Use product analysis techniques such as product breakdown and systems analysis to
decompose the system testing work package
b) Decompose the system development work package now and decompose the system testing
work package later
c) Break down the project into multiple phases so that the system testing work package goes
into the second project phase
d) Consult the project management plan to determine what to do in this situation
18) You are part of a project team designing a new type of a vehicle. You are about to begin work on
a work package for the braking system of the vehicle and want to review the acceptance criteria before
starting the work. Where can you find this information?
a) Project management plan
b) Activity attributes
c) Requirements documentation
d) The WBS dictionary
19) Two team members are arguing over how to organize the work packages in the work breakdown
structure (WBS). One says the work packages should be arranged in the order the work is planned to
be carried out, while the other insists the order of the work packages in the WBS does not matter. The
two ask the project manager for advice. What is the project manager's best response?
a) Work is decomposed and sequenced in the Define Activities process.
b) Any approach is good as long as the team members avoid the conflict.
c) The chronological order of tasks is defined in the Sequence Activities process.