11. A company manages SBG contracting bids for government tenders and all successful
bids as a separate project. The structure of the company is mainly projectized for a
dedicated project team to manage each project. However, to realize economies of
scale, there are some central departments that serve all projects. Which of the
following role is most likely to be working in a central department instead of directly
working with a project team?
A) Quality control inspector
B) Construction manager
C) Project planner
D) Procurement administrator
12. The performance reports produced during the Control Procurements process are then
provided to which project management process for further processing?
Al_Monitor & Control Project Work in the form of work performance information
B) Direct & Manage Project Work in the form of work performance data
C) Perform Integrated Change Control in the form of a change request
D) Performance report is not an output of the Control Procurement process
13. You are managing a complex submarine causeway construction project. When you
started the project, the scope of work was not clear and was based on a rather high-
level estimate. Now that you are in the middle of the project, more information has
become available. As a result, you now need to change some of the key subcontracts
on the project. Which of the following will guide you through the change process?
A) Change control terms of the individual subcontracts
B) Project management plan's change control procedures
C) Organizational process assets
D) Supplier's contract administrator
5