a) Discuss the benefits of constructing a WBS when carrying out a Project.
(5 marks)
b) Develop a possible Work Breakdown Structure (WBS) for the above project, your
WBS must include at least FIVE summary tasks as well as subtasks.
(20 marks)
Question Three
[25 marks]
a) Analyse the importance of Human project management processes and describe the
typical activities carried out in each process.
(15 marks)
b) Recently, you promoted your star programmer, Sam, to lead the development team.
Sam was a fantastic software coder, and you thought the promotion would mean that
he could now share his expertise with the other development team members.
However, you are surprised to learn that the promotion is now causing some conflicts
in the team.
(10_marks)
Question Four
[10 marks]
Imagine you have been recently employed to be part of a Project Team. The Surveyor Pro
project which has a concept for developing a sophisticated information system that includes
expert systems, object-oriented databases, and wireless communications. The system should
provide instant, graphical information to help government surveyors do their jobs. For
example, after a surveyor touches a map on the screen of a handheld device, the system
should prompt the surveyor to enter the type of information needed for that area. This system
should help in planning and implementing many projects, from laying fiber-optic cable to
installing water lines.
Your task allocated to you is to DEVELOP a cost estimate for this project
Required
Design a possible Cost Estimate Plan assuming the university has a budget of $N1.5million
(10 marks)
[THE END]