QUALIFICATION{S): DIPLOMA IN PROPERTYSTUDIES
BACHELOROF PROPERTYSTUDIES
QUALIFICATION(S)CODE: 06DIPS
08BOPS
COURSECODE: BSS511S
EXAMSSESSION:JUNE 2024
DURATION: 3 HOURS
NQF LEVEL: 5
COURSENAME: BUILDING SERVICES
PAPER:
THEORY
MARKS:
100
EXAMINER(S)
FIRSTOPPORTUNITY EXAMINATION QUESTION PAPER
MS ELINA TEODOL
MODERATOR: MR VERINJAERAKO KANGOTUE
INSTRUCTIONS
1. Read the entire question paper before answering the Questions.
2. Please write clearly and legibly!
3. The question paper contains a total of 4 questions.
4. You must answer ALLQUESTIONS.
5. Make sure your Student Number is on the EXAMINATION BOOK(S).
PERMISSIBLEMATERIALS
1. Non-programmable Scientific Calculator
THIS QUESTION PAPERCONSISTSOF 10 PAGES(Including this front page)

2 Page 2

▲back to top


Building Services
B55511S
Question 1
Choose the correct answer for each of the following multiple-choice questions. Each correct answer carries 1
mark.
(20}
a} Which system is responsible for removing wastewater and sewage from buildings?
A} Electrical Systems
B} HVAC Systems
C} Plumbing Systems
D}Fire Safety Systems
b} What is the primary role of a Building Management System (BMS}?
A} Security surveillance
B} Manage building aesthetics
C}Monitor and manage building's mechanical and electrical equipment
D}Exclusively control the building's lighting systems
c} Which certification assesses buildings for sustainability?
A) ISO9001
B} BREEAM
C}FCC
D} ASIC
d} Which type of HVAC system allows for individual temperature settings in different zones?
A} Forced air systems
B} Central HVACsystems
C}Variable Refrigerant Flow (VRF}systems
D} Window units
e} What does the integration of sustainable design in building construction aim to minimise?
A} Initial construction costs
B) Energy use
First Opportunity Examination Paper
Page 2 of 10
June 2024

3 Page 3

▲back to top


Building Services
C) Building height restrictions
D) Time required for construction
BSS511S
f) A new office building has consistently experienced power outages and flickering lights. What is the
most likely issue to investigate first?
A) Inadequate plumbing systems
B) Overloaded electrical circuits
C) Faulty HVACsystems
D) Inefficient building insulation
g) During a retrofit of a historical building, which HVACsystem would be least disruptive to install?
A) Large central ducted systems
B) High-velocity, small duct systems
C) Extensive radiant floor heating
D) Large-scaleforced air units
h) A hospital is planning to improve its air quality to prevent the spread of infections. Which feature
should be prioritised?
A) Increased natural ventilation
B) Installation of HEPAfilters in the HVACsystem
C) Adding more air conditioning units
D) Reducing the number of air exchanges per hour
i) A building manager wants to reduce energy costs using the existing BMS. Which strategy should be
implemented first?
A) Increase the setpoint temperature for air conditioning
B) Implement occupancy-based lighting control
C) Replace all lighting with LEDlamps immediately
D) Install additional sensors for better data collection
First Opportunity Examination Paper
Page 3 of 10
June 2024

4 Page 4

▲back to top


Building Services
B5S511S
j) A design team is aiming for a high LEEDcertification for a new commercial building. What sustainable
design element is essential to achieve this?
A) State-of-the-art gym facilities
B) High-performance building envelope
C) Luxury finishes in interior design
D) Use of exotic building materials
k) During a summer heatwave, a newly constructed office building reports significantly higher
temperatures on the top floor compared to lower floors. What could be a primary factor in this issue?
A) Insufficient roof insulation
B) Inadequate window shading on the top floor
C) Faulty fire alarm systems
D) Inefficient plumbing systems
I) A project manager must choose a heating system for a large, open-plan office building in a cold
climate. Which system would provide the most consistent heat distribution and energy efficiency?
A) Portable electric heaters placed strategically around the office
B) Radiant floor heating systems throughout the office space
C) Centralised forced air heating with few ducts
D) Individual space heaters at each workstation
m) An architect is designing a building in a high-density urban area with limited accessto natural light.
Which strategy should be prioritised to enhance indoor environmental quality?
A) Incorporation of a central atrium with skylights
B) Use of dark, heat-absorbing exterior materials
C) Installation of small, tinted windows
D) Reduction of communal space to increase window surface area per office
First Opportunity Examination Paper
Page 4 of 10
June 2024

5 Page 5

▲back to top


Building Services
B5S511S
n) Which technology would best improve energy efficiency in a building where employees complain
about varying temperatures and drafts?
A) Standard thermostats placed in every room
B) High-volume low-speed (HVLS)fans in central locations
C)Zoned HVACsystems with smart thermostats
D) Increased use of space heaters in colder areas
o) In a renovation project for an old building, which update would most significantly improve
sustainability and energy efficiency?
A) Replacing all existing windows with triple-glazed windows
B) Applying a new coat of paint to all exterior walls
C) Installing new carpeting throughout the building
D) Upgrading the aesthetic design of the fa<;:ade
p) A building is being designed in a tropical climate. Which feature is crucial to minimise heat gain and
reduce cooling loads?
A) Deep window overhangs and shaded facades
B) Extensive use of glass walls for natural light
C) High ceilings with no fans
D) Closed spaces with minimal windows
q) A facility manager is tasked with reducing water consumption in a corporate building. Which initiative
should be implemented first?
A) Installation of water-efficient toilets and urinals
B) Increase the price of bottled water in the cafeteria
C) Ban on personal water bottles
D) Reduce the operating hours of the building's water fountains
First Opportunity Examination Paper
Page 5 of 10
June 2024

6 Page 6

▲back to top


Building Services
BSSSllS
r) For a building located in an earthquake-prone area, which engineering solution is essential to enhance
safety and durability?
A) Lightweight roofing materials
B) Earthquake-resistant structural design
C) Increased use of glass in exterior design
D) Installation of traditional HVACsystems
s) What is the primary benefit of integrating smart meters and energy management systems in building
operations?
A) They reduce the need for manual security systems.
B) They provide real-time data to optimise energy usage and cost.
C)They eliminate the need for any HVACsystems.
D) They decrease the importance of interior design.
t) A developer wants to ensure that a new residential complex adheres to sustainability standards. Which
certification should the building aim to obtain?
A) ISO9001 Quality Management
B) BREEAMor LEEDEnvironmental Design
C)Six Sigma Efficiency Standards
D) FDA Health Compliance
[20]
Question 2
a) Distinguish between the following terms as used in building services.
i) Variable Refrigerant flow and Central HVACsystems
ii) Green Energy and Renewable Energy
iii) Greywater and black water systems in buildings
iv) Fire detection systems and fire suppression systems
First Opportunity Examination Paper
Page 6 of 10
(4)
(4)
(4)
(4)
June 2024

7 Page 7

▲back to top


Building Services
v) Occupancy sensors and daylight sensors in building management systems
BSS511S
(4)
[20)
Question 3
Case Study: The Edge, Amsterdam
{30)
Overview:
The Edge, located in Amsterdam, is renowned for its state-of-the-art sustainable design and has been
dubbed one of the world's greenest buildings. Developed by PLP Architecture, The Edge incorporates a
myriad of advanced technologies and sustainable practices, notably in energy management, water
conservation, and smart systems integration.
Building Services Integration:
Energy Efficiency: The building is equipped with an extensive array of solar panels that cover not
only the roof but also the south-facing facades, contributing to its nearly energy-neutral status. It
generates approximately 1,000,000 kWh per year, while consuming about 800,000 kWh.
Lighting and Climate Control: Utilizing an advanced LED lighting system integrated with daylight
harvesting and occupancy sensors, The Edge optimises lighting use based on natural light availability
and room occupancy. The climate system employs ground-source heat pumps and thermal energy
storage.
Water Management: The building features a rainwater harvesting system that collects water for
toilet flushing and landscape irrigation, reducing reliance on municipal water systems. Annually, it
captures about 300,000 litres of rainwater.
Connectivity and Automation: A digital ceiling connects Ethernet-powered LED fixtures, creating a
responsive and adaptable environment. Employees control their local environment via smartphone
apps, contributing to personal comfort and overall building efficiency.
Use the Hypothetical Data provided below to perform all calculations:
Energy Generated: 1,000,000 kWh/year.
Energy Consumed: 800,000 kWh/year.
Conventional Building Energy Consumption: 1,500,000 kWh/year
Rainwater Used: 300,000 litres/year.
First Opportunity Examination Paper
Page 7 of 10
June 2024

8 Page 8

▲back to top


Building Services
Conventional Building Water Consumption: 600,000 litres/year for similar uses
Lighting Energy Consumption Before LED Integration: 200,000 kWh/year
Lighting Energy Consumption After LED Integration: 120,000 kWh/year
a) Energy Efficiency Analysis
BSSSllS
i) Calculate the net energy surplus of The Edge based on the energy generated and consumed. (4)
ii) Compare the energy efficiency of The Edge with a conventional building using the provided data.
(2)
iii) Calculate the percentage energy savings achieved by The Edge over the conventional building.
(4)
iv) Draw a bar chart to compare the energy consumption of the Edge and a conventional building
and clearly label the chart. Provide a brief discussion under the chart explaining what the chart
demonstrates and any insights it provides into the Edge's sustainability and efficiency practices.
(4)
b) Water Management Analysis
i) Analyse the effectiveness of the rainwater harvesting system at The Edge by calculating the
percentage of water saved compared to a conventional building. Use the given data to support
your calculation.
(6)
ii) Draw a pie chart to illustrate the water usage at The Edge, showing the proportion of rainwater
used versus potable water.
(4)
c) Amart Building System Impact Analysis
i) Calculate the percentage reduction in energy consumption for lighting before and after the
integration of LEDlighting and smart controls.
(4)
ii) Discuss how smart building systems (like automated lighting and climate control) can enhance
overall building efficiency. Support your answer with calculations from the provided data. (4)
iii) Draw a bar chart to show the reduction in lighting energy consumption before and after the
integration of LEDand smart controls.
(4)
(36]
First Opportunity Examination Paper
Page 8 of 10
June 2024

9 Page 9

▲back to top


Building Services
8555115
Question 4
Case Study: EcoHomes Residential Development
Overview:
The EcoHomes Residential Development is a theoretical project aimed at integrating advanced sustainable
building services in a modern residential complex. This development includes specific features for energy
efficiency, water conservation, and advanced home automation systems to enhance resident comfort and
reduce environmental impact.
Sustainable Building Services:
1. Energy Systems:
• The development includes rooftop solar panels and high-efficiency appliances paired with smart
meters for real-time energy monitoring.
2. Water Management:
Rainwater is harvested to supply water for landscaping and flushing toilets. High efficiency
plumbing fixtures are installed to reduce water usage.
3. Lighting:
LEDlighting is used throughout, managed by smart controls that adjust based on occupancy and
daylight availability.
4. HVAC:
• The development uses a geothermal heating and cooling system. Smart thermostats allow for
automated temperature adjustments based on external weather conditions and interior
occupancy patterns.
Questions:
a) Describe how solar panels contribute to the sustainability of EcoHomes.
(4)
b) What role do smart meters play in managing energy consumption?
First Opportunity Examination Paper
Page 9 of 10
(4)
June 2024

10 Page 10

▲back to top


Building Services
B5S511S
c) How does rainwater harvest benefit the EcoHomes project?
d) Explain the significance of using high efficiency plumbing fixtures.
e) Evaluate the impact of smart controls on lighting efficiency in EcoHomes.
f) Discussthe benefits of smart thermostats integrated with geothermal HVACsystems.
(4)
(4)
(4)
(4)
[24]