SECTION B — Essay Type Questions (80marks)
Question 1
Create a new Work-Breakdown Structure (WBS) for a small project with the following
elements: developing a new technology product, design phase, programming phase, testing
phase, first design phase and second design phase
(20 marks)
Question 2
The communication plan is an important part of a project planning. As a newly appointed
project manager, you are facing the following situation: The project needs to begin on 3
March 2020. Before the project can commence, the team needs to be built. The first project
team development meeting is scheduled for 6 February 2020. The project assistant is
requested to send an agenda via email for the meeting on 15 January 2020 to all team
members. Later, on 22 January 2020, he needs to call all team members to invite them
personally to participate in a project team development programme. On 15 February 2020,
the project manager will send the project team development document via email to all team
members in order to inform them about the procedure.
You are requested to create the communication plan with appropriate headings by using
the data supplied above. Plan carefully and allocate correct information in a table.
(20marks)
Question 3
Draw a diagram of a typical project life cycle showing the phases and state 8 advantages
for developing a life cycle.
(20 marks)
Question 4
Explain what is meant by a project environment and support with examples
(20 marks)
TOTAL FOR SECTION B: 80 MARKS
THE END.
TOTAL FOR THIS TEST: 100 MARKS