d. The unloading bay is currently staffed by two employees who are each paid
$100 for a 40 hour week, with any overtime being paid at a 4/3 rate. A
suggestion has been made that a third person should be employed in the
unloading ay which, it has been estimated, would result in saving of seven
minutes in the average time to unload a lorry. This, it has been claimed, would
not only reduce the lorry waiting time but would also produce a saving in cost
to the mine. Analyse this suggestion and make a recommendation. [8]
2. A construction company has just made the winning bid of $5.4 million to construct a
new plant for a major manufacturer. The manufacturer needs the plant to go into
operation within a year. Therefore, the contract includes the following provisions:
• A penalty of $300,000 if the company has not completed construction by the
deadline 47 weeks from start.
• To provide additional incentive for speedy construction, a bonus of $150,000 will be
paid to the company if the plant is completed within 40 weeks.
a. The following details pertaining to the project. Construct the network diagram and
compute the project completion time.
[ 10]
Table 1: Activities description and predecessors
AcUvlty
A
B
C
D
t
F
G
H
I
J
K
L
M
N
Activity Description
E.xc.:ivate
L'ly the foundntion
Pul up th rough willl
Put up the roof
IIHUlllthe cxtcr or plumbing
lrulllll thl! interior plumbing
Pul up the e,,cterior .siding
Do the exterior pciintlng
Do th<?electrical work
Put up the wallboa.rd
!mt.ill the flooring
Do the intimor pilintlng
IIHtall the cxterlor fllCtur~
!rut.all the mtcrlor fixtures
lmmC?dlate
Pr~CCC!SSOrs
-
A
8
C
C
E
D
E, C
C
F, l
J
1
H
K, L
Table 2: Activity times