SECTION B: STRUCTURED QUESTIONS (60 MARKS)
QUESTION 2
Using the Value Risk Matrix (VRM), apply your understanding, analyze and provide a classification of
the contract into one of the following categories: Strategic, Leveraged, Routine, or Focused? Your
justification is critical in answering this question based on the contract's value and associated risks.
(20 Marks)
2.1 The Walvis Bay Municipality, a Namibian based Public Entity, is considering outsourcing its IT
services for a contract valued at N$50 million. (2 Marks)
2.2 Ongwediva Medipark Hospital, a leading hospital chain, is entering into a procurement contract
for the servicing of respiratory support medical equipment valued at N$20 million. (2 Marks)
2.3 ABC Electronics, a leading manufacturer of consumer electronics, requires specialized packaging
materials for its new line of high-end smartphones, with a contract value of N$1 million. (2 Marks)
2.4 GHI Pharmaceuticals is engaging in a contract for the development of a new drug, with a contract
value of N$150 million. (2 Marks)
2.5 JKLCorporation, a manufacturing company, is outsourcing its logistics operations for a contract
valued at N$30 million. (2 Marks)
2.6 MNO Bank is procuring a new core banking system for a contract value of N$80 million. (2 Marks)
2.7 A government agency is entering into a contract with Waltons Namibia for the provision of office
stationery, with a contract value of N$500 000.00. (2 Marks)
2.8 The Roads Authority concluded a contract after an Open National bidding process for the
construction of a highway. STU Construction Company was awarded the contract with a value of
N$900 million. (2 Marks)
2.9 See-Through IT Services, a large multinational company, is negotiating a software licensing
agreement with a leading software vendor for its enterprise resource planning (ERP)system, with
a contract value of N$500 million. (2 Marks)
2.10 YZA Retail Chain is entering into a contract for the supply of transportation services from a new
service provider, with a contract value of N$100 000.00 (2 Marks)
Subtotal: 20 Marks
QUESTION 3
The Namibia Standards Institution as a public sector organization is planning to construct a new head
office building to accommodate its growing workforce and enhance operational efficiency. The
construction of the office building is estimated at an amount of N$ 100 million, and estimated to take
3 years to complete. The procurement process involves several stages of contract management and
stakeholders.
Using the provided example, analyse each stage of the contract management process and identify the
key activities, stakeholders and considerations involved in each stage? (20 Marks)
QUESTION 4
Apart from the contract agreement itself, what other documents should be included in the content of
a procurement contract arising from a public procurement process? (6 Marks)
8