SECTION A: MULTIPLE CHOICE QUESTIONS [Ql.1- Q 1.60] [TOTAL MARKS - 60]
1. A communication management
communicated to.
A. the project team
B. the project stakeholders
C. the project board
D. the project sponsor
plan identifies the relevant information
that should be
2. Which one of the following statements is true?
A. Independent reviews and quality audits form part of quality assurance to ensure the
project manager delivers on time and to budget
B. Quality assurance provides confidence to stakeholders that requirements for quality will
be exceeded
C. Quality control verifies that the project deliverables conform to specification, are fit for
purpose and meet stakeholder expectations
D. Quality planning enables the project manager to manage the trade off between customer
expectations and budget
3. Project risk management is best described as.
A. managing responses to threats
B. identifying and acknowledging threats and opportunities
C. planning responses to threats
D. minimising threats and maximising opportunities
4. Which one of the following best describes a project issue?
A. A major problem that requires formal escalation
B. A problem that the project manager has to deal with on a day to day basis
C. An uncertain event that may or may not occur
D. An opportunity that occurs through change control
5. Scheduling can best be defined as the process used to determine.
A. overall project duration
B. project cost estimating
C. the project management plan
D. sub contractors responsibilities
6. Which one of the following statements is true?
A. An increase in project scope is likely to increase project cost
B. A decrease in the project time is likely to increase project quality
C. An increase in the project quality requirements is likely to decrease project cost
D. A decrease in the project cost is likely to decrease project time
7. Which one of the following statements best defines the purpose of a Product Breakdown
Structure?
A. To define the hierarchy of deliverables that are required to be produced on the project
B. To define how the products are produced by identifying derivations and dependencies
C. To establish the extent of work required prior to project commissioning and the handover
21Page