QUESTION 1
(10 Marks]
(a) Define project management.
{2 Marks)
(b) Define 'Terms of Reference' as used in Project Management.
(1 Mark)
(c) What is a Work Breakdown Structure?
(2 Marks)
(d) Please give two (2) reasons why projects fail in Namibia.
(2 Marks)
(e} One of the stages of a project cycle is the appraisal (ex-ante analysis}. Briefly
explain what this stage entails.
(3 Marks)
QUESTION 2
[60 Marks]
In order to develop a personnel performance appraisal software package for a company, a list of
items needs to be considered. Use the data and worksheet to develop an estimate of the project
cost. Resources: Designers (100 hrs@$50/hr}, Systems analysts (200 hrs@$40/hr), Programmers
(approximately 5000 lines of code with a production rate of SOlines/hr and cost rate of $35/hr),
Workstation ($1500), Contracted testing group {SO hrs@$75/hr), Printing of user manuals
($1000}.
Overhead: 70% of Direct Wages.
Fringe benefits: 30% of (Overhead + Direct Wages).
Show all your calculation steps.
NB: Marks will be awarded for each correct computation 1 each total figure and for the
layout. [60 marks]
QUESTION 3
[20 Marks]
Time is the most valuable thing a person can spend.
(a) Display your understanding of project planning by writing down reasons why time
management is important during project implementation. (Provide any 5 points) (5 Marks)
(b} Gantt Charts are important to ensure successful development projects! Explain? (Provide
any 5 points with explanations)
(10 Marks)
2