SECTIONA
Question 1
[20 MARKS]
[10 x 2 = 20 marks]
Choosethe correct option and indicate your choice (A-D) next to the appropriate number in the
examination book provided. For example 1. 8.
1. Project management is a discipline with a strong foundation in a well-defined, well-
documented established body of knowledge. This is known as the:
A. PM80K.
8. PMI.
C. POM8K.
D. AM8K.
2. The purposes of
______
should be to determine whether the project provided the
customer with the expected benefits, assessthe level of customer satisfaction, and obtain any
feedback that would be helpful in future business relationships with this customer or with other
customers.
A. a post-project evaluation meeting with the customer or sponsor
8. a project progress meeting with project stakeholders
C. an analysis session with the project team
D. a pre-RFPmeeting with the customer
3. Risks__ should be given higher priority because if the risk occurs, it would have a greater
impact on the schedule than if it was associated with activities on a path that has a large positive
value of total slack.
A. that occur first in the project
8. that affect the most costly activities
C. on the critical path
D. that affect the activities near the end of the project
4. Projects documents are organised and archived in the
A. initiating phase.
8. planning phase.
C. performing phase.
D. closing phase.
5. The project objective is usually defined in terms of
A. all the constraints for the project.
8. the end product or deliverable, schedule, and budget.
C. initiating, planning, executing, and controlling.
D. the project scope.