1.10 Project attributes are;
A. Collection of programs, Unique purpose, set for a period, that considers uncertainty.
B. Set for a period, with a unique purpose, developed with elaboration, considering
uncertainty with a primary sponsor.
C. Has a unique purpose considering uncertainty and a set period, with no sponsor and
progressive elaboration?
D. A permanent program with a unique purpose developed through progressive
elaborations while considering uncertainty with no sponsors.
1.11 Which of the following statements best describes a project scope?
A. The processes required to ensure that the project includes all the work required, and
only the work required, to complete the project successfully.
B. The features and functions that characterize a product, service, or result.,·,
C. The work performed to deliver a product, service, or result with the specified features
and functions. The term "project scope" is sometimes viewed as including product
scope.
D. The scope management plan is a component of the project or program management
plan that describes how the scope will be defined, developed, monitored; controlled,
and validated.
1.12 Which of the following statements best describes a product scope?
A. The processes required to ensure that the project includes all the work required, and
only the work required, to complete the project successfully.
B. The features and functions that characterize a product, service, or result.
C. The work performed to deliver a product, service, or result with the specified features
and functions. The term "project scope" is sometimes viewed as including product
scope.
D. The scope management plan is a component of the project or program management
plan that describes how the scope will be defined, developed, monitored,controlled,
and validated.
1.13 A Project Charter includes:
A. Precedence diagramming methods
B. Task estimates
C. Detailed resource estimates
D. The business need for the project
1.14 The customer wants to make a major change in the project scope when the project is
mostly complete. The project manager should.
A. Make the change
B. Inform the customer of the impact of the change
C. Refuse the change
D. Complain to management
Page 4 of6