1. Which of the following is an advantage of using project management:
a. Increased Efficiency & Productivity
b. Cost and Complexity
c. Shorter development times
2. Which of the following is not an example of a project?
a. A retail store manager works with employees to display a new clothing line
b. A college campus upgrades its technology infrastructure to provide wireless Internet
access.
c. A full-time TVET Trainer at WVTC training her trainees.
3. Which of the following attributes does not define Projects?
a. A project has a unique purpose
b. A project is permanent
c. A project is made of a cross-functional team
4. Triple constraint or "iron triangle" refers:
a. Time
b. Risk
c. Scope
5. Which of the following aspects is not a tool/technique of Scope management?
a. Scope statements
b. Work breakdown structures
c. Net present value
6. Process Groups elements of project management include:
a. Closing
b. Scope
c. Risk
7. A Project has succeeded if:
a. The results of the project met its main objective
b. The project dissatisfied the customer/sponsor
c. The project did not meet scope, schedule, and cost goals
8. Knowledge areas elements of project management include:
a. Monitoring and Evaluation.
b. Planning
c. Schedule.
9. Strategic and business management skills needed by Project Managers include:
a. Understanding the process groups
b. Understanding the knowledge areas
c. Marketing
10. Communication management in project management includes:
a. Kickoff meetings
b. Ghant charts
c. Cost baselines