SECTIONB: STRUCTUREDQUESTIONS(40 MARKS)
QUESTION2 (10 MARKS)
Using the Value Risk Matrix (VRM), apply your understanding, analyse and provide a
classification of the contract. Your justification is critical in answering this question based on
the contract's value and associated risks.
2.1 Your organisation is negotiating a contract worth N$2.5 million annually with a cloud
service provider to manage your entire IT infrastructure. The contract will impact every
department in the organisation. There are significant risks if the service fails, including
data loss and operational disruption.
2 Marks
2.2 A contract worth N$25,000 annually is being signed with a supplier for standard office
stationery. The contract poses little to no operational risk. Multiple suppliers can offer the
same products at similar prices.
2 Marks
2.3 Your facilities department has entered a contract valued at N$150,000 annually for the
regular maintenance of HVAC systems. The service is crucial during peak seasons, like
summer, to avoid operational breakdowns. Alternative suppliers are available, but
switching may cause temporary service disruption.
2 Marks
2.4 A new contract worth N$1.8 million (one-time purchase) is being negotiated to purchase
a highly specialised piece of manufacturing equipment unique to your production line.
The supplier is one of only two available globally. Any failure or delay in delivery could halt
production for weeks.
2 Marks
2.5 The HR department is entering a contract valued at N$100,000 annually with a catering
company for in-house events and staff lunches. Several vendors offer similar services. The
risk is relatively low, as there are many alternatives in case of dissatisfaction. 2 Marks
QUESTION3 (10 MARKS)
In 2023, EcoBuild Ltd., a mid-sized construction firm, was awarded a contract worth N$100
million by the Central Procurement Board of Namibia on behalf of the Ministry of Works and
Transport to build a government office complex in Windhoek, Namibia. The project was
scheduled to be completed within 12 months.
A liquidated damages clause was included, stating:
"The Contractor shall be liable to pay the Employer liquidated damages of 0.1% of the
Contract Price per calendar day, up to a maximum of 10% of the total Contract Price,
for failure to complete the Works by the Time for Completion, unless an extension of
time has been approved by the Engineer."
The contract liquidated damages equates to a penalty of $100,000 per day for delays beyond
the agreed completion date. The employer argued:
o Delays were not formally notified as per the contract's requirement.
4